Enter an Extension of Time

For example we will enter an extension of time for a contract.  This may occur due to bad weather, unforeseen construction circumstances, or at the client’s request.

1.   Ensure Contract Management is open

2.   Select a Contract and click on Properties
For example choose the contract [Groundworks for Shed] for the job [Industrial Shed].

3.   Click on the Extensions of Time Register tab

4.   Click on New

5.   Enter of From – To range date 
The From date will be today’s date.  We will enter a To date.  Click on the To date selection button, and choose a date 2 weeks from now.

6.   Click in the Days Affected field

7.   Notice that the days affected is automatically calculated for you.  

8.   Select a Delay Type using the drop down menu selection 
For example choose [2 - Weather] 

9.   Enter details for Who Affected, Reference and Comment Leave the “Status” to Pending
For example enter the Who Affected as: [Ground works and concreters], leave the Status as [Pending], and enter a Reference of [Rain], with Comments as [You can’t stop the weather!]

10. Click on OK to confirm

11. Select the Extension of time we just entered, and click on Properties

12. Change the Status to Approved and click on OK
A confirmation message will be displayed, asking you if you want to add the days on to the completion of the project

13. Click Yes to the message 

14. Click on OK to close the Contract Maintenance