The Zavanti Housing implementation will follow these phases. The plan and timetable will be developed in conjunction with you through our Planning workshops:
|
Phase |
Main Objectives |
Major deliverable/tasks |
|
Planning |
•Analysis & Implementation Planning, environment D365 setup |
•Project Kick-off meeting •Project Management Plan •Project schedule •Ascertain Resources •MS Dynamics 365 setup •Deploy standard “Sandbox” |
|
Requirements Gathering & configuration |
•Workshops •Overview of each module •Reviewed configurable items |
•Staff understanding from each Workshop for each housing module •Configuration updates for client “sandbox” •Matters identified for Decision |
|
Design & Build |
•Final Configuration •Data migration planning •Installation services •Customisation development, as required and agreed |
•Production Database creation and configuration •Data Migration Plan •Production Zavanti Housing platform sign off •Training plan |
|
System testing |
•Implement pilot system •System Testing |
•Pilot operation & System testing •Database review and update as necessary |
|
Data Migration and Integration |
•Populate data to pilot •User Acceptance Testing trial |
•Pilot full operation •Database review and update as necessary |
|
User Acceptance Testing (UAT) |
•Client to perform (UAT) User Acceptance Testing •Process and workflow Acceptance Testing |
•Database review and update as necessary •Report issues for fixing •User Acceptance validated cases |
|
Training |
•Client User training •Process and workflow |
•Train the Trainer •User training completed •User Acceptance training Sign off |
|
“Go Live” |
•Deliver configured production system •Final data migration |
•Support transition commenced •User “Go Live” Sign off |