Maintaining a 'Committed' amount different to the PO details amount

A new default setting "Allow to modify PO Commitment Value" is available in PO Defaults, and when checked, if the JOB is set to Authority level 1 - no checking, then the user is able to change the PO committed value on the BUDGET TAB in the PO maintenance window, and the Job PO window With this option set the user must SAVE the PO committed value on the BUDGET TAB of the PO maintenance window by clicking OK when on the BUDGET TAB. To SAVE the PO committed value on the BUDGET TAB of the JOB PO window, the user must click off the Budget TAB, before leaving the Job PO window Please note that if the Job Authority setting is NOT level 1, then the "Budget" tab has been disabled, and the Budget details can be reviewed on the Details TAB (as present).