The read only field provided on this TAB window that will show the calculated “Estimated Completion Date” This date will be set and reset to the ‘last task’ scheduled date, as it is calculated based on the rules shown above, or as entered directly into the Task management window
A read field is provided on this TAB window that will show the calculated “Estimated Completion Date” in an 'ORIGINAL ESTIMATED COMPLETION DATE" field when the user initially assigns a schedule to the Job When we add a NEW Schedule to a JOB and set or RESET the START Date, i.e. UNTIL we DISABLE the START DATE and WORK SCHEDULE, this can change.
A field “DELAY DAYS” will show the number of days difference + or -from “ORIGINAL EST COMPLETION” VS ‘EST COMPLETION”. These values will also be shown on the report
E.g. Original Estimated Completion Date: 25 Feb 2024
Estimated Completion Date: 26 Feb 2024 (recalculated each time)
Delay Days: 1 (Recalculated)
This will show the user if the job is running late or early.